Lucent Technologies ECS Minicell Battery Plant H569-420
Issue 5 February 1997
Installation 5 - 3
6. All bolts making electrical connections should be torqued
per the values in Table 5-A; all bolts for mechanical
connections should be torqued per values in Table 5-B.
Installation
Sequence
Table 5-C lists the drawings, manuals and other documentation
that are necessary to complete the following Sequence of Tasks.
Unpacking,
Handling, and
Frame
Installation
1. Before opening the packaging, carefully inspect the
outside, in the presence of shipping personnel, for signs of
damage. If damaged, follow the shipping carrier's
procedure for filing a damage claim.
2. To ensure personnel safety and equipment protection use
appropriate equipment during handling of crates and
uncrated equipment. Use the equipment weights and
dimensions given in Section 2 as a guideline for choosing
material handling tools. Move crated equipment to an area
with adequate space and tools for unpacking and handling.
3. Carefully open the packaging to verify that the contents are
complete and undamaged. If the equipment must be
returned, it should be repacked in the original shipping
crate.
Battery Stand
Assembly
Assemble battery stands per the battery manual. Install the
batteries onto their stands.
Warning
Do not connect batteries to the system at this time.