Lucent Technologies Lineage
®
2000 ECS Battery Plant H569-416
3 - 24 Engineering, Planning & Ordering
Issue 2 August 1996
necessary instructions to the installer for the controller set-up.
Refer to the J85501D-2 controller drawing and the Controller
Manual for details.
Alarm System
Interface
The standard ECS controller is equipped with connection points
for a variety of battery plant alarms. The wiring from the
controller alarm points to the local and remote reporting alarm
systems is NOT provided with the battery plant. Such wiring
must be compatible in gauge and type with the terminal blocks
provided on the controller circuit packs, as detailed in the
Controller Manual.
Earthquake
Bracing
The earthquake ratings for the standard ECS battery plant is:
Zone 4, upper floors, per NEBS TR-EOP-000063.
Appearance
Packages
An appearance package option is available for the initial and
supplementary bays of the ECS battery plant. This option is
shown in Figure 3-1. It includes Front Style Strips (846651115
List KA), which are metal covers used to improve the aesthetics
of the plant by covering the frame uprights, concealing the
equipment mounting screws, and providing an enclosed cable
way. A right and left style strip is provided with this option.
For additional information and installation details refer to the
H569-416 drawing.