• Use a 63.5 mm (2.50 in.) or larger supply pipe to provide the correct flow to four 19 mm (0.75 in.) supply
hoses, with a 120 kW CDU.
• Use an 88.9 mm (3.50 in.) or larger supply pipe to provide the correct flow to nine 19 mm (0.75 in.) supply
hoses, with a 300 kW CDU.
To stop the flow of water in individual legs of multiple circuit loops, install shutoff valves for each supply and
return line. This provides a way to service or replace an individual heat exchanger without affecting the
operation of other heat exchangers in the loop.
To ensure that water specifications are being met and that the optimum heat removal is taking place, use
temperature and flow metering (monitoring) in secondary loops.
Anchor or restrain all manifolds and pipes to provide the required support and to avoid movement when
quick-connect couplings are being attached to the manifolds.
Figure 66 “The following figure” on page 60 shows another layout for multiple water circuits.
Figure 66. Typical central manifold (at a central location for multiple water circuits)
Figure 67 “The following figure” on page 61 shows an extended manifold layout.
60
ThinkSystem Heavy Duty Full Depth 42U Rack Cabinet User Guide
Summary of Contents for ThinkSystem Heavy Duty Full Depth 42U Rack Cabinet
Page 1: ...ThinkSystem Heavy Duty Full Depth 42U Rack Cabinet User Guide Machine Type 7D6D ...
Page 4: ...ii ThinkSystem Heavy Duty Full Depth 42U Rack Cabinet User Guide ...
Page 16: ...12 ThinkSystem Heavy Duty Full Depth 42U Rack Cabinet User Guide ...
Page 23: ...Figure 19 Rising the leveling pads Chapter 3 Rack cabinet setup 19 ...
Page 146: ...142 ThinkSystem Heavy Duty Full Depth 42U Rack Cabinet User Guide ...
Page 152: ...148 ThinkSystem Heavy Duty Full Depth 42U Rack Cabinet User Guide ...
Page 153: ......
Page 154: ......