5.3.1. Power Connections
The power screw terminals are located on the lower front side of the UPS.
Firstly, open the UPS door, screw out of the metal cover, afterwards open plastic cover of terminals.
After the covers are removed, the cables shall be passed through the hole under the terminals.
After all connections done, replace the covers in order.
10-30kVA KEOR T
40-60kVA KEOR T
Make sure that all circuit breakers are “OFF” before starting with the installation.
Figure.5.3.1-1
Figure.5.3.1-2
Figure.5.3.1-3
Figure.5.3.1-5
Figure.5.3.1-4
Summary of Contents for 30 KVA
Page 1: ...KEOR T 10 60 KVA INSTALLATION MANUAL ...
Page 4: ...IV Installation Operating Manuals Battery Fast Fuses ...
Page 30: ...25 KEOR T 10 30kVA 1x60pcs 7 9Ah BATTERY WIRING DIAGRAM Figure 5 3 1 4 1 ...
Page 31: ...26 KEOR T 10 30kVA 2x60pcs 7 9Ah BATTERY WIRING DIAGRAM Figure 5 3 1 4 2 ...
Page 32: ...27 KEOR T 40 60kVA 2x60pcs 7 9Ah BATTERY WIRING DIAGRAM Figure 5 3 1 4 3 ...
Page 33: ...28 KEOR T 40 60kVA 3x60pcs 7 9Ah BATTERY WIRING DIAGRAM Figure 5 3 1 4 4 ...
Page 46: ...41 Appendix 3 Description of UPS and Block Diagram SEPARATED RECTIFIER AND BYPASS INPUTS ...