5.
Insert a membrane into vessel #2 if a two membrane system. The end with the seal will go into the vessel first
and will be at the bottom of the vessel when in place. Use caution when installing the membrane – ensure the
seal remains in the grooves of the membrane as it is installed in the vessel.
6.
Insert the vessel caps into the top of the vessels and secure with the
clamps. The cap with valve V2 and the pressure gauge will go on vessel #2
of a two membrane system (on the single vessel on a single membrane
system).
Daily
Each day, it is recommended the following be done:
1.
Inspect the prefilter. If it is dirty or had a “slimy” coating - change the prefilter.
2.
Remove, clean and reinstall the strainer in the Y-strainer.
3.
Sample the permeate liquid;
a.
Purge the permeate line by running the system and drawing a volume of permeate to a test cup.
b.
Test the permeate sugar level using either a refractometer or a hydrometer.
c.
If the results indicate there is any sugar present there is a possible problem with the membrane O-
rings or alignment coupling. Check the troubleshooting chart.
4.
Check all hoses, piping, fittings and connections for leaks. Repair as necessary.
5.
Run a cycle of Desugar (see page 27) and Alkaline Soap Wash (see page 29)
6.
Do a Permeability test (see page 21)
7.
Inspect and clean storage tanks
a.
Permeate
b.
Concentrate
c.
Sap
End Of Season Shutdown and Storage
If permeate is not available to perform the rinse and wash cycles stated in the following procedure, obtain the
necessary volume of water using non chlorinated well or spring water.
The following flow chart outlines the steps to follow for the first steps in preparing the system for shutdown. Note
the text version follows in Steps 1 – 4.