7 Servicing/Maintenance
47 of 92
ILN / ILNC / ILNR
5211.8/08-EN
NOTE
All sealing elements affected by the dismantling process must be replaced.
DANGER
Insufficient preparation of work on the pump (set)
Risk of injury!
▷
Properly shut down the pump set. (
▷
Close the shut-off elements in the suction line and discharge line.
▷
Drain the pump and release the pump pressure. (
▷
Shut off any auxiliary connections.
▷
Allow the pump set to cool down to ambient temperature.
NOTE
After a prolonged period of operation the individual components may be hard to
pull off the shaft. If this is the case, use a brand name penetrating agent and/or - if
possible - an appropriate puller.
7.4.2 Preparing the pump set
1. De-energise the pump set and secure it against unintentional start-up.
2. Reduce pressure in the piping by opening a consumer installation.
3. Disconnect and remove all auxiliary pipework.
7.4.3 Dismantling the pump set: ILN
7.4.3.1 Dismantling the complete pump set
NOTE
The pump casing can remain installed in the piping for further dismantling.
ü
The notes and steps stated in (
Section 7.4.2, Page 47) have been observed/carried out.
1. Disconnect the discharge nozzle and suction nozzle from the piping.
2. Depending on the pump/motor size, remove the supports from the pump set.
3. Remove the complete pump set from the piping.
7.4.3.2 Removing the motor
WARNING
Motor tipping over
Risk of crushing hands and feet!
▷
Suspend or support the motor to prevent it from tipping over.
ü
The notes and steps stated in (
Section 7.4.3.1, Page 47) have been observed/carried out.
1. Remove hexagon head bolt 901.3.
2. Remove the motor.
Summary of Contents for ILN
Page 1: ...In line Pump ILN ILNC ILNR Operating Manual ...
Page 89: ...Index 89 of 92 ILN ILNC ILNR 5211 8 08 EN W Warnings 8 Warranty claims 7 ...
Page 90: ......
Page 91: ......