5 Operation
20 of 34
Deep Lift System
2553.89/04-EN
901.03
897
901.01
59-11
71-14
901.03
594
Fig. 8:
Fitting the connection pipe, weights and guide piece
1. Fasten connection pipe 71-14 to support frame 594 with fastening screws
901.03. (
2. Slide weights 59-11 onto connection pipe 71-14. Secure them with fastening
screws 901.01.
3. Fasten guide piece 897 to support frame 594 with fastening screws 901.03.
Adjusting the connection pipe, weights and guide piece
897
901.01
59-11
71-14
Fig. 9:
Adjusting the connection pipe, weights and guide piece
1. Extend guide piece 897 to its maximum length.
2. Attach the crane hook to the lifting accessory.
3. Slightly lift the lifting accessory with a crane.
ð
The lifting accessory should be suspended from the crane in a horizontal
position.
If required, adjust its position by moving the weights as follows.
4. Place the lifting accessory down in a suitable place.
5. Undo fastening screws 901.01. Move weights 59-11 along connection pipe 71-14
as required.
6. Tighten fastening screws 901.01 to secure weights 59-11.
7. Slightly lift the lifting accessory with a crane to re-check the position of the
lifting accessory. If required, keep adjusting the position.
Pulling out the pump set
DANGER
Persons in the sump
Danger to life from falling parts!
▷
Make sure that nobody is in the sump while the pump is being lowered or
pulled out.