5 Installation at Site
33 of 126
Amacan K
1579.807/07-EN
1
2
4
6
3
5
Fig. 18:
Lifting and positioning the pump set
2. Secure the lifting chain or lifting rope (1) to the trolley (4) of the lifting
equipment (2).
3. Attach the support rope (5) to the bail by its shackle. Check that the support
rope is arranged with the lifting lug (6) pointing away from the pump set.
4. Partially unwind the support rope and electric cables.
5. Lower the pump set into the discharge tube until the bail is in an accessible
position, protruding from the discharge tube.
6. Securely cover the discharge tube except for a gap which allows work to
continue.
7. Attach the first lifting lug of the support rope (5) to the lifting rope (1) to
securely position the pump set above the discharge tube.
8. Unclip the hook of the lifting equipment from the lifting lug of the support
rope and run the lifting equipment to a higher level.
7
8
9
Fig. 19:
Securing the control cable and power cables
9. Secure the control cable (7) and power cables (8) to the crane hook (3) of the
lifting equipment with a manila rope (9).
10. Trim the spacer (a) to fit between the two ferrules.