69
9. Commissioning
9.1. Inspection before Commissioning
Check the following items before starting the system:
1. The inverter DC switch and external circuit breaker are disconnected.
2. The inverter should be accessible for operation, maintenance and service.
3. Nothing is left on the top of the inverter or battery.
4. The inverter is correctly connected to the external devices, and the cables are routed in a
safe place or protected against mechanical damage.
5. The selection of the AC circuit breaker is in accordance to this manual and all applicable
local standards.
6. All unused terminals at the bottom of the inverter are properly sealed.
7. Warning signs and labels are suitably affixed and durable.
8. For EPS application, check the cable connections of inverter. Risk of inverter damage if the
grid power wires are wrongly connected to the EPS terminals.
Can set the power quality mode through the following steps.
Step 1: Press the "Enter" button in the main interface to ENTER the interface below, select
the "Settings" option through the "Up" button and the "Down" button, and then press
the "Enter" button to ENTER the next level menu
.
Step 2: After entering the following menu, select the option of "Power regulation setting"
through the "Up" and "Down" buttons, and then press the "Enter" button to Enter the
next menu.
Step 3: After entering the following menu, enter the password through the "Up" button and
"Down" button to enter the next menu. Power management information is an important
parameter, in order to ensure the safety of users and set, password can be obtained
by consulting customer service.
Step 4: Enter the correct password, enter the following menu. The user can select the power
quality mode to be set by "up" and "Down" (there are two modes, as shown in Figure
1), and then press "ENTER" to confirm. After the Settings are successful, the system
displays OK, and press Esc to return to the home screen.
Summary of Contents for KY-EST06KH
Page 1: ...1 User Manual 3 Phase Hybrid Inverter KY EST06KH KY EST20KH V1 0...
Page 10: ...10 Dimensions KY EST06 10KH unit mm Dimensions KY EST12 20KH unit mm...
Page 12: ...12 Fig1 5 Three phase Meter Dimension unit mm...
Page 15: ...15 Each successive press of the button selects a new parameter...
Page 16: ...16 Each successive press of the button selects a new parameter...
Page 17: ...17 Each successive press of the button selects a new parameter...
Page 32: ...32 View the power quality response mode...
Page 34: ...34 Figure 5 2 2...
Page 68: ...68...
Page 70: ...70 Figure...