4.1.2. The boiler should be placed on a steel surface according to the
figure 1.
4.1.3. The boiler must be set in a position which allows the easiest
possible cleaning and maintaining (see figure 1).
4.1.4. Take out air flap adjusting screw, scoop and scraper from the
combustion chamber.
4.2. Connecting the cooling coil.
The “KORDI-10S” boiler is equipped with safety cooling coil. It connects
to the water system through a thermostatic valve. In a case of overheating,
the thermostatic valve feeds in cold water that passes through the cooling
coil and absorbs the heat in the boiler. The draining valve discharges it into
the sewage system. This device ensures safe evacuation of the excess heat
without the need of user’s presence. The cooling coil guarantees that the
water in the boiler will not exceed the maximum safe level of 95 ºC
We recommend to connect the safety cooling coil according to figure 4.
Figure 4. Connecting the safety cooling coil
ATTENTION! Stop the operation of the boiler if the
cooling coil is faulty.