STEP TEN
Install the control panel (Part B) (C-25 for 120V and
C-85 for 240/208V/) on the post with the power sup-
ply. Use the #10 x 1” long or longer screws and the
screw placements on the control panel to secure the
panel to the post.
NOTE:
The control panel must be
hung upright in order to be rain tight.
STEP ELEVEN
Set Timer in the control panel to desired ON and OFF
times per the Instructions on page 9 for the C-25 or
page 10 for the C-85.
Make sure to test the GFI us-
ing the Test Button located on the outlet before
turning the equipment on and every 30 days thereaf-
ter.
STEP TWELVE (For 120V Installations)
Plug the aerating fountain cord into the C-25 outlet
labeled “UNIT”. If lights are included, plug the
Transformer cord into the C-25 outlet labeled
“LIGHT”. Now you are ready to plug the C-25 into
the 120V power supply on the post and
ENJOY
YOUR NEW KASCO AERATING FOUNTAIN!
STEP TWELVE (For 240/208V Installations)
Hardwire the 240/208V, 4 wire service into the C-85
control panel per the Instructions on page 10 of this
manual. It is essential that each leg is equal and no
more than 120V for the equipment to work properly.
The aerating fountain can either be plugged into the
240V outlet on the right hand side of the C-85 panel
or hardwired into the panel.
PLUG:
Insert the plug on the unit into the outlet and
securely close the outlet cover until it snaps into
place.
Test the GFCB with the test button now and
every 30 days.
HARDWIRE:
The bottom of the C-85 control panel
has several knock-outs for hardwiring the unit. Re-
move a knock-out that is not used for the main power
as well as the internal metal barrier plate in the panel.
Remove the plug from the power cord on the unit and
strip back 12” of cord jacket to expose the wires (2
hot and 1 ground). With the main power discon-
nected, connect the bare wire (stripped) portion of the
GREEN ground wire to the grounding strip at the bot-
tom of the panel and secure tightly. Locate and re-
move the plastic shield under the yellow timer (black
or clear depending on model). Under shield, lug #2
and #4 are LOAD lugs. Loosen the screws and insert
the bare wire (stripped) portion of the WHITE wire
into #2 and the bare wire (stripped) portion of the
BLACK wire into #4. Tighten both lugs securely.
Test the GFCB with the test button now and every
30 days.
If lights are installed, they can now be wired
per Instructions on page 10 of this manual.
Once completed, power can be restored to the panel.
ENJOY YOUR NEW KASCO AERATING
FOUNTAIN!
7