Application note -
Grid standby operation for blueplanet hybrid 10.0 TL3
APL_ Grid_Standby_Operation_for_
blueplanet hybrid 10.0 TL3
Status: 2022-08-08
Page 5 of 8
5.3
Condition and setting
The following conditions apply:
•
A battery must be connected.
•
The device must be connected to the grid (AC) during configuration to check the phase position.
•
The phase position must be correct on the device and on the hy-switch.
•
PV power must be present during configuration because the device will restart.
•
The SOC must be at least 10% for switching to standby power operation.
Furthermore, the following settings must be entered:
NOTE
HT
The software can be used for grid parallel operation and temporary standalone mode (standby power
operation). Switching can occur automatically.
The corresponding setting must be entered in the
hy-sys
user software from version 7.
Unpack the firmware package, e.g. 7.12.10.4.11, on your computer.
Open the hy-sys software.
Log in to the hy-sys software as an installer.
Update the software on your device on the Update tab in the following order:
1)
COM (blueplanet hybrid 10.0 TL3 COM 7_10.edu)
2)
CONTROLLER (blueplanet hybrid 10.0 TL3 Controller 7_12.edu)
3)
HY-SWITCH (blueplanet hy-switch 7_4.edu)
Load the certificate for standby power operation onto the unit.
The certificate is loaded onto the device in the
User Settings
tab under
Activation Certificate
.
Note:
The certificate for standby power operation is device-specific. If you do not have a certificate file, please
contact KACO Service and have your proof of purchase ready.
TAB User Settings: Right Upload of the certificate, centre Check function for the phase position