45
Document Number
DCV-00206
Date Released
Dec. 2016
Revision Number/Security level
R00 S2
Retrofit G7+InvencoLink Wayne Ovation (US) Installation Guide
5 First Power-Up
Once the installation is complete and the wiring is certified (if necessary), power may be applied.
The G7 OPT takes a couple of minutes to complete its start-up phase, during which several information
screens will be presented.
The terminal will display the following screen whilst attempting to connect to the LAN. This screen will
persist until a connection can be made:
If the terminal is successful in connecting to the LAN it will display the following screen and the rest of the
start-up sequence will continue: