2. On the second screen you select the language to view the display menus.
Please, select an option
Please, select an option
Highlight the desired language via the keys
and
and press
.
3. From this menu you can select the current date and time. Upon accessing the year flashes. Change with
the keys
and
. Press
to go on to select the date. Follow this process to select the day, time,
minutes and seconds.
4. Here we select the country or regulation governing the inverter.
Once a general visual inspection, wiring check and sealing check have been carried out, connect power to the unit
(DC and AC).
In the first inverter connection a number of screens appear in which you must select, in this order, language,
country and applicable standards. After its configuration a feedback screen appears with the options selected.
After this first configuration, select
Main menu > Start/Stop > Start
, thus starting the inverter. If it does not
connect, open the installation switch and check the polarities of the PV array.
100
First connection to the grid
Ingeteam
ABE2011IQM01_C - Installation and Operation Manual
Summary of Contents for INGECON SUN 1Play TL M
Page 58: ...Anmerkungen Notes Notas Remarques Note Notas...
Page 108: ...Anmerkungen Notes Notas Remarques Note Notas...
Page 309: ...Anmerkungen Notes Notas Remarques Note Notas...
Page 310: ...Anmerkungen Notes Notas Remarques Note Notas...
Page 312: ...Ingeteam Power Technology S A www ingeteam com ABE2011IQM01_C 06 2016...