21
UK
D2
150 mm
R
►
The lower edge of the process connection should be flush with the installation
environment (see fig� 6-5)�
►
Avoid non-flush installation (see 6-6)�
►
Use seals or washers (see D in fig� 6-7) to reach the required height�
6.4.4 Installation in plastic tanks
150 mm
R
To enable sufficient transfer of the measured signal, note in case of installation in
plastic tanks or metal tanks with plastic lid:
►
A drill hole with a minimum diameter of 150 mm must be applied to the plastic
lid�
►
For installation of the unit, a flange plate (= launching plate R) must be used
which sufficiently covers the drill hole�
►
Ensure the minimum distance (= 80 mm) between rod and tank wall, higher for
probe lengths > 70 cm and in case of heavy soiling (→ 6.1.1).