GAS BOILER SYSTEM COMMISSIONING CHECKLIST & WARRANTY VALIDATION RECORD
Address:
Boiler make and model:
Boiler serial number:
Commissioned by (PRINT NAME):
Company name:
Telephone number:
Company email:
Company address:
Commissioning date:
Heating and hot water system complies with the appropriate Building Regulations?
Yes
Optional: Building Regulations Notification Number (if applicable):
Water quality
The system has been flushed, cleaned and a suitable inhibitor applied upon final fill, in accordance with boiler manufacturers’ instructions
Yes
What system cleaner was used?
Brand:
Product:
What inhibitor was used?
Brand:
Product:
Primary water system filter
pre-existing
Fitted
Not required
CENTRAL HEATING MODE measure and record (as appropriate)
Gas rate (for combination boilers complete DHW mode gas rate)
m
3/
hr
or
ft
3
/hr
Central heating output left at factory settings?
Yes
No
If no, what is the maximum central heating output selected?
kW
Dynamic gas inlet pressure
kPa
Central heating flow temperature
°C
Central heating return temperature
°C
System correctly balanced/rebalanced?
Yes
COMBINATION BOILERS ONLY
Is the installation in a hard water area (above 200ppm)?
Yes
No
Water scale reducer/softener
pre-existing
Fitted
Not required
What type of scale reducer/softener has been fitted?
Brand:
Product:
Water meter fitted?
Yes
No
If yes- DHW expansion vessel
pre-existing
Fitted
Not required
Pressure reducing valve
pre-existing
Fitted
Not required
DOMESTIC HOT WATER MODE Measure and record
Gas rate
m
3/
hr
or
ft
3
/hr
Dynamic gas inlet pressure at maximum rate
kPa
Cold water inlet temperature
°C
Hot water has been checked at all outlets
Yes
Temperature
°C
CONDENSATE DISPOSAL
The condensate drain has been installed in accordance with the manufacturers’ instructions
Yes
Point of termination
Internal
External (only where internal termination impractical)
Method of disposal
Gravity
Pumped
ALL INSTALLATIONS
Record the following
At max rate:
CO
ppm CO
2
%
CO/CO
2
Ratio
At min rate (where possible)
CO
ppm CO
2
%
CO/CO
2
Ratio
Where possible, has a flue integrity check been undertaken in accordance with manufacturers’ instructions, and readings are correct?
Yes
The operation of the boiler and system controls have been demonstrated to and understood by the customer
Yes
The manufacturers’ literature, including Checklist and Service Record, has been explained and left with the customer
Yes
Commissioning Engineer’s signature
Customer’s signature
(To confirm satisfactory demonstration and receipt of manufacturers’ literature)
Time, temperature control and boiler interlock provided for central heating and hot water
Yes
6 COMMISSIONING & SERVICING