Minimiser
- Installation
38
Refer also to Frame 10 - 'Boiler exploded view'. & Frame 37 - 'Pictorial wiring'.
1.
Refer to Frame 58.
Note.
The sealing panel need not be removed.
2.
Remove the boiler bottom panel - refer to Frame 59, step 4.
3.
Open the controls pod door and pull off the thermostat knob.
4.
Undo the control box securing screw and swing the box into the 'servicing'
position. If access if restricted pull the box forward and free from the boiler -
refer to Frame 59.
SERVICING
72 PRINTED CIRCUIT BOARD REPLACEMENT
74 CONDENSATE SIPHON REPLACEMENT
73 'BURNER ON' NEON REPLACEMENT
Refer also to Frame 37 - Pictorial Wiring.
1.
Refer to Frame 58.
Note.
The sealing panel need not be
removed.
2.
Swing the control box into its 'servicing' position - refer to
Frame 72, steps 1-4 .
3.
Unplug the 'Burner on' neon lead from the PCB - refer to
Frame 72.
4.
Prise the neon out of the lens holder.
5.
Fit the new neon and re-assemble in reverse order.
SER
VICING
3
4
a
6.
Squeeze the retaining tabs on the two location pins and
withdraw the PCB, complete with the other 2 pins.
Transfer these pins to the new PCB..
7.
Fit the new PCB and re-assemble in reverse order.
Ensure that all electrical connections are correctly
remade.
8.
Check the operation of the boiler.
5.
Unplug the following leads from the PCB:
a.
Gas valve lead
b.
Flame detection lead
c.
'Burner on' neon lead
d.
Fan lead
e.
Mains input lead
b
c
d
e
PCB
37
Fuse
Siphon
6
Refer also to Frame 10 - 'Boiler exploded view'.
1.
Refer to Frame 58.
2.
Remove the fan unit - refer to Frame 53.
3.
Remove the gas injection pipe - refer to Frame 67, step 8.
4.
Disconnect the spark and detector leads - refer to Frame 63.
5.
Disconnect the condensate drain from the bottom of the boiler.
6.
Undo the siphon union connection.
7.
Push the siphon down slightly to clear the union, tilt
forward and withdraw it from the boiler.
8.
Fit the new siphon and reassemble in reverse order,
replacing any damaged or deteriorating sealing gasket.
5
6
6
2
4
3
LED