Slide rails
Use this procedure when your system is installed using slide rails.
Before you begin
Notes:
v
When placing the system into the service position, it is essential that all stability plates are firmly
installed to prevent the rack from toppling. Ensure that only one system unit is in the service position
at a time.
v
Ensure that the cables at the rear of the system unit do not catch or bind as you pull the system unit
forward in the rack.
v
When the rails are fully extended, the rail safety latches lock into place. This action prevents the
system from being pulled out too far.
Procedure
1.
Remove the screws on either side of the system that secure the system to the rack.
2.
Push down the front latches (A) that secure the system unit to the rack.
3.
Pull the system unit out of the rack.
Fixed rails
Use this procedure when your system is installed using fixed rails.
Before you begin
CAUTION:
This system requires two people to remove the system from the rack. Do not begin this procedure
unless physical assistance is available to remove the system from the rack.
Figure 67. Placing the system into the srvice position
Common procedures for servicing or installing features
99
Summary of Contents for S822LC
Page 2: ......
Page 16: ...xiv Installing the System and Ordered Parts for the 8335 GCA or 8335 GTA...
Page 104: ...88 Installing the System and Ordered Parts for the 8335 GCA or 8335 GTA...
Page 122: ...106 Installing the System and Ordered Parts for the 8335 GCA or 8335 GTA...
Page 125: ...Figure 78 Connecting the power cord to the power supply Power supplies 109...
Page 126: ...110 Installing the System and Ordered Parts for the 8335 GCA or 8335 GTA...