8. System installation AeroFix
Before constructing the PV system the roof must be cleared of dirt, snow and ice.
Base rails
The assembly of the base rail G2 and G2 Eco is idendical.
Measure roof and mark out edge and corner areas
Install base rails with integrated building protection mat
Fig. 13 Roof preperation
Fig. 14 Installation base rails
Summary of Contents for AeroFix 10-EW
Page 1: ...1 Installation instructions IBC AeroFix AeroFlat Version 20 01 Date 20 July 2020...
Page 9: ...9 Version 20 01 20 July 2020 4 2 AeroFlat Parallel to the roof Fig 6 AeroFlat...
Page 17: ...17 Version 20 01 20 July 2020 Fig 15 Installation base rails Fig 16 Installation base rails...
Page 42: ...42 Version 20 01 20 July 2020 Fig 61 Wind plate assembly Fig 62 Fixation wind plate...
Page 53: ...53 Version 20 01 20 July 2020 Fig 81 Schematic system dimensions...
Page 68: ...68 Version 20 01 20 July 2020...
Page 71: ...71 Version 20 01 20 July 2020 13 4 Checklist IBC AeroFix...
Page 72: ...72 Version 20 01 20 July 2020...