Installation
Sec. 7 Pg. 1
Installation
Step
Procedure
Selecting Position for
Boat & Hoist
1.1
Fig. F1
Pull the
boat
into the boat slip so that the bow can be easily reached from the front of
the slip. Allow at least 12 inches of space between the dock and the boat, at the dock
level, in the event the boat may need to be later moved in final positioning.
1.2
With the boat in the desired location, place a mark on the dock where the boat’s
transom is positioned.
Note
: Do not include extensions to the hull such as swim
platforms; the transom mark should reflect the location of the
end of the bottom of the
hull.
1.3
Remove the boat and pull the
hoist
into the slip.
1.4
Position the hoist along side the dock and align the
rear end
of the Hull Support Pads
with the
transom mark
on the dock.
1.5
With the hoist held stationary at this position, place
marks
on the dock at the location
of the
Rear Mooring Assembly
and the
Front Mooring Assembly
.
Step
Procedure
Mooring the Hoist
2.1
Fig. Q
Move the hoist into position and align the
rear
Mooring Assembly [21] with the
mark
on the dock.
2.2
Fig. R
Place the Mooring Cover [22] over the Mooring Assembly [21] and the Slider [23]
over the Mooring Cover [22]. Securely attach the Slider [23] of each Mooring Assem-
bly to the dock. This may be done with a suitable rope of 3/4” diameter (max.). The
tab
on the Slider should be positioned
away
from the dock.
Fig. Q
HydroHoist International, Inc.
Model: 9/12/15/17B
Publication: 8/24/04
Fig. R
Summary of Contents for Side-Tie 12B
Page 10: ......
Page 31: ...T WOT A N KH O I S T S H O S ED I A G R A M F O U RT A N KH O I S T S...
Page 36: ......