Refer to Figure 13
disassembly
1 . Remove all external items previously dis-
cussed in their recommended order .
2 . Remove the external retaining ring (169)
and discard . Remove the 2-speed arm
(168) .
NOTE:
Only remove the 2-speed lock-down
arm (165) if damaged. Mark the orien-
tation before removal.
3 . Remove the screw (167) and the washer
(166) .
4 . Remove the 2–speed lock-down arm
(165) .
5 . Remove the seal (164) and discard .
NOTE:
Only remove the seal (164) if damaged
or worn, or if doing a complete disas-
sembly.
2–speed arm (OpTIOnal)
figure 13, 2- speed arm
Inspection
1 . Inspect the 2–speed actuating handle (168)
and the 2–speed lock-down arm (165) for
excessive wear or damage . Replace if nec-
essary .
assembly
1 . Reassemble all parts in the reverse order
of disassembly .
2 . Install the new seal (164) from seal kit .
3 . Install the 2–speed lock-down arm (165),
washer (166) and screw (167) . Refer to the
table on page 15 for the required torque
values .
4 . Install the 2-speed actuating arm (168) .
screw (167) .
5 . Install the new external retaining ring
(169) .