Chapter 4 • Commissioning the satellite modem
52
1039434-0001 Revision A
4. In the Warning dialog that warns that the transmitter is actively powered on
during the manual cross-polarization test, click
Continu
e
.
Figure 33: Manual cross-polarization warning message
The Cross Pol Test window displays the test status, isolation value, and pass/fail
result.
Figure 34: Manual cross-polarization test results
5. Adjust the antenna during the manual cross-polarization test to achieve
maximum transmit isolation.
6. Lock down the antenna adjustment when the modem consistently passes the
manual cross-polarization test.
7. Click Close to close the Cross Pol Test window.
8. On the Transmit Antenna Pointing screen, click
Automatic
to initiate the ACP
test.
9. If the modem fails ACP, re-peak the transmit isolation in manual
cross-polarization test mode.
10. If the modem passes ACP, click
Close
to close the Cross Pol Test window.
Ku-band pointing is now complete.
11. What you do now depends on whether you are using satellite-based or manual
commissioning:
•
If you are using satellite-based commissioning, click
Next
on the Transmit
Antenna Pointing screen to continue.
•
If you are following the instructions for Ku-band manual commissioning, click
Exit
; then go to
Software download-manual commissioning
on page 61.
Summary of Contents for HN9260
Page 28: ...Chapter 3 Installing the satellite modem 28 1039434 0001 Revision A ...
Page 62: ...Chapter 4 Commissioning the satellite modem 62 1039434 0001 Revision A ...
Page 84: ...Chapter 6 System control center 84 1039434 0001 Revision A ...
Page 88: ...Chapter 7 LEDs 88 1039434 0001 Revision A ...
Page 112: ...Appendix B Updating the modem software 112 1039434 0001 Revision A ...
Page 116: ...Appendix C Standards compliance 116 1039434 0001 Revision A ...