Figure 9-2
Securing cables on the tower
Special Cabling Requirements
Cabling Requirements for Power Cables
l
Power cables must be installed in the position specified in engineering design documents.
l
If the length of power cables is insufficient, replace the cables rather than adding connectors
or soldering joints to lengthen the cables.
l
Cables must be routed by only qualified and trained personnel before all preparations are
made.
l
Cables are routed in an untangled and orderly fashion.
l
If DC power cables need to be routed on the tower platform, lay out the cables on the
guardrail with the shortest distance and route the cables along the guardrail.