6 Commissioning Guide
Issue 03 (2018-01-25)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
69
6
Commissioning Guide
6.1 Check Before Power-on Commissioning
Table 6-1
Hardware installation checklist
No.
Check Item
Result
1
The cabinet is clean, without redundant screws, copper
wires, or other debris.
□Yes □No
2
The paint on the cabinet exterior is intact.
□Yes □No
3
The cabinet door and lock work properly.
□Yes □No
4
All labels are correct, clear, and complete.
□Yes □No
5
The surrounding area of the cabinet contains no waste tape,
cable ties, paper, or packing materials.
□Yes □No
Table 6-2
Electrical connection checklist
No.
Check Item
Result
1
All cables are connected properly.
□Yes □No
2
The ground cable is connected properly.
□Yes □No
3
The excessive sections of ground cables and power cables
are cut off.
□Yes □No
4
Phase cables are connected properly.
□Yes □No
5
All circuit breakers are OFF.
□Yes □No