Figure 4-42 Securing an outdoor unit to the ground
----End
Securing an Outdoor Unit to the Base
NO TICE
The following takes the two-layer installation of outdoor units as an example. For
the single-layer installation, perform only
and
Step 1 Secure the first-layer base to the ground using six M12x60 stainless steel
expansion anchor bolts, as shown in
Figure 4-43 Securing a base
NO TE
Only four bolts are required to secure the NetCol500-A060 double-layer base to the ground.
Step 2 Secure the four columns.
NetCol5000-A050 In-row Air Cooled Smart Cooling
Product
User Manual
4 Installation
Issue 08 (2021-09-17)
Copyright © Huawei Technologies Co., Ltd.
72