10
WFS 1545 Operations Manual
Before verifying that the platform is level, insure all four of the
leveling legs are firmly on the floor. If any leg is not touching the
floor, adjust by loosening the leveler lock nut and winding this ½ - 13
nut in a clockwise direction. Once the leg is firmly on the floor, wind
the upper locknut (above the underside of the equipment base) in a
clockwise direction until tight. Complete by winding the exposed ½-
13 locknut ‘up’ in a counter-clockwise direction until tight. Next,
using a bubble level or similar leveling tool, measure the level of the
equipment base. Place the
level-tool
in an unobstructed surface of
the equipment base. If the equipment is off-level by less than ¼
bubble, no adjustment is necessary. However, if more than ¼ adjust
the respective legs accordingly. Ensure all leg locknuts are tight.
e.
CHILLER ASSEMBLY
WARNING:
Avoid personal injury. Installing the chiller and attaching the control panel requires lifting and
maneuvering heavy and bulky items. Use proper equipment and have adequate unobstructed room for
safe installation
After uncrating move the WFS base to an area where the chiller can be safely installed.
Remove the shrink wrap holding the control panel on the chiller support frame and carefully
support the control panel off to the side next to the Base frame.
1
CAUTION
:
Use care not to damage the flexible conduit going to the motors or other cables.
1
For units with optional sensors the cables can be unplugged from the sensor to allow easier handling of the control
cabinet.
Remove shrink wrap
from control panel and
set down on side next
to the base.
FIGURE 4
FIGURE 5