1 Getting started
This chapter provides information about required kits and reference documentation. Check that you
have met the requirements and have all the required materials before you begin the upgrade procedures
described in this guide.
IMPORTANT:
To upgrade from an HSV200-A or HSV210-A controller to an HSV200-B or HSV210-B controller,
HP requires that you also upgrade the I/O modules (A and B) to AD623C and AD624C on each
shelf. If you are upgrading to an EVA6100 (HSV200-B) or EVA8100 (HSV210-B) and you do not
already have the 30-10022-01 loop switches installed, you must also upgrade the loop switches to
30-10022-01. See the
HP StorageWorks 4x00/6x00/8x00 Enterprise Virtual Array user guide for
more information.
Upgrade overview
Depending on the upgrade path for your configuration, an upgrade can be done either online or
offline.
•
During an
online upgrade
, EVA controller software is upgraded while the controllers are receiving
I/O; the controllers resynchronize simultaneously, and both hosts and applications continue to
run. The resynchronization during an online upgrade represents a single disruption of I/O, not
the multiple disruptions seen with some upgrade types. However, you must consider host and ap-
plication timeouts when doing an online upgrade.
•
During an
offline upgrade
(shutdown upgrade), all host I/O to the storage system must be stopped.
All applications and hosts are shut down before the controller upgrade is done, and restarted
when the upgrade is complete.
An offline upgrade requires scheduling time with application managers, and having staff on hand
to shut down and restart applications and hosts. While actual upgrade time may be short, offline
upgrades can require several hours to complete from the start of the first application shutdown
until all hosts and applications have returned to service.
HP StorageWorks 4x00/6x00/8x00 Enterprise Virtual Array Updating Product Software Guide (XCS
6.220)
9
Summary of Contents for 6100
Page 8: ...8 ...
Page 44: ...Pre upgrade tasks 44 ...
Page 64: ...Upgrading the Enterprise Virtual Array 64 ...
Page 66: ...Downgrading the Enterprise Virtual Array 66 ...