Appendix A - Site Preparation Kit
This Appendix contains the following information:
•
Pre-installation Worksheet
•
Space Planning Kit
•
System power requirements and heat dissipation worksheets
Hewlett-Packard recommends that you copy the worksheets before you begin using them. Then, if
more copies are needed in the future, you will have an unmarked copy of the worksheets available.
Pre-Installation Worksheet
Table A-3.
Pre-Installation Activities
.
Timing
Activity
✓
Date
6 weeks before installation
Select the location for the system. Use the Site
Preparation Guide to satisfy any requirements to
ensure the site is ready when the system arrives.
❑
Assign a person the responsibility of system prin-
cipal operator.
❑
Plan the physical arrangement of the system and
its peripherals. The space planning kit allows you
to plan details before the system arrives.
❑
Order supplies that are required for uninterrupted
operation of the system (consumable supplies).
❑
At system delivery
Inspect each shipment as it is delivered. Note
comments and dates in shipment schedule.
❑
When all equipment arrives, contact the CE to
schedule the installation and verify that the site
meets the system requirements. Installation will
be scheduled within three working days after
Hewlett-Packard has been contacted.
❑
System installation
Arrange for the system manager to assist the CE
with the installation process.
❑
Summary of Contents for 3000/9x9KS Series
Page 10: ...x ...
Page 38: ...A 4 Figure A 1 Space Planning Grid Sheet ...
Page 39: ...A 5 Figure A 2 System Cutouts ...
Page 70: ...B 28 ...
Page 75: ...C 5 Figure C 3 Space Planning Grid ...
Page 76: ...C 6 Figure C 4 K Class Equipment Profiles ...
Page 77: ...C 7 Figure C 5 T Class Equipment Profiles ...
Page 82: ...C 12 ...