1-3
Table 1-1. Site Preparation Technical Tasks.
Technical Tasks
Responsible Personnel
Line voltage measurement
Electrician and Customer Engineer (CE)
Line voltage measured
Electrician and Customer Engineer (CE)
Power line frequency measured (if required)
CE
Power line noise levels measured (if required)
CE
Neutral or ground noise/voltage levels measured
CE
Safety and ground connections verified
Electrician and CE
Advice on correct circuit breakers and wire size
Electrician and CE
Verification that maintenance power outlets
(those used for floor cleaning, etc.) are on sepa-
rate circuits from the computer system
Electrician and CE
Recommendations about lightning protection
CE
Measurements and recommendations on radiated
interference
CE
Answers to questions concerning modems and
modem options
Applications Engineer (AE)
Thermal load of HP equipment
CE
Thermal load of non-HP equipment
Customer and Equipment Vendor
Modifications to Existing Electrical Service
Electrician and Customer
Modifications to Existing Air Conditioning
A/C Contractor and Customer
Environmental Contaminants
CE and Environmental Engineer/Contractor
Placement of Equipment (For Service Access)
CE
Summary of Contents for 3000/9x9KS Series
Page 10: ...x ...
Page 38: ...A 4 Figure A 1 Space Planning Grid Sheet ...
Page 39: ...A 5 Figure A 2 System Cutouts ...
Page 70: ...B 28 ...
Page 75: ...C 5 Figure C 3 Space Planning Grid ...
Page 76: ...C 6 Figure C 4 K Class Equipment Profiles ...
Page 77: ...C 7 Figure C 5 T Class Equipment Profiles ...
Page 82: ...C 12 ...