Step 6: Connection of the front section to the Side Floor
Profiles:

Now attach both Side-Floor Profiles (#1.2) to the front section by
inserting the aluminum-corner connectors with recessed screws
while at the same time sliding the Curved Corner Profiles (#2.1)
into the Side-Floor Profiles. Tighten the recessed screws. (See
picture on left).

Now you will need a third person or devices that can help
you hold the profiles in the air.

Step 7 :  Mounting of Curved Center Profiles with 2 Channels

:

Now slide a Curved Center Profile with 2 Channels (#2.2) from the
rear to the front into Side-Floor Profiles (#1.2)  Be sure the end
marked with the X is on the bottom. Slide to about 45“ from the
front Corner Profiles.

F ix ing  –  on the front
with s heet meta l s crews
4,2x 13

Step 8: Mounting of the Roof Beam Profile #1.3:

Lift the Roof Beam (#1.3) and, coming from the back, thread the 2
Curved Center Profiles into the channel of the Roof Beam.
Continue moving the roof beam forward until reaching the front
Curved Corner Profiles and thread them onto the end of the Roof
Beam.Cover the end using the Roof Beam Cover plate and fasten
with sheet metal screws 4,2x13

. (See picture on left). Note: Use

3 people for this step: Two to hold up the Curved Profiles and
one to slide the roof beam while standing on a stepladder.

Step 9 :  Adding additional Curved Center Profiles #2.2

:

Now add more Curved Center Profiles as necessary (Series II
uses only 1 on each side; III uses 2 on each side and IV uses 3
on each side). Slide each along the Side-Floor Profile as well
as the Roof Beam at the same time. Be careful to move the
profile only inches at a time on each end. Preferably one
person pushes at the bottom while the other pushes at the top.
Use Rubber Mallet!  Distance between each set  is about 45“.

Important information regarding the Mounting of Polycarbonate Glazing Panels:

Warning

:

 

Always put the side with the blue protective film towards the outside.

All glazing panels come coated with a special layer of high quality U V  inhibiting film,
however this treatment is only applied on one side. In order to identify the U V -coated side a
removable layer of blue protective film has been applied. This film must be removed before
placing the Glazing Panels into any of the channels of the aluminum profiles. Remove
protective film from both sides only one panel at a time as you

 

install each panel.

Suggestion:

 Mark either the inside or the outside of each panel with a dot from a permanent

marker. That way if you later move the greenhouse you will always know which side of the
panels is coated. The Glazing Panels are not marked. Choose the right one like solving a
puzzle! Have a little fun.

Warning

:

 Do not leave Glazing Panels with the protective film in bright sunlight as the film

                 will be permanently glued to the Panels.

Detail A

Detail E

Summary of Contents for Riga 2 S/2

Page 1: ... M I N U M O n io n s h a p e d g r e e n h o u s e R ig a Assembly Instructions R IG A S eries II III IV November 2004 Riga Ty p e 3 Tec h n ic a lIn forma tion S u bjec t to C h a n g e M a d e in G erma n y ...

Page 2: ...t of the U nited States H igh intensity sunshine is not good for more than a few hours a day In such areas some protection from trees and or buildings is recommended Shade cloth might also be needed ask your supplier for details F or greenhouses intended for grow ing vegetables such as tomatoes cucumbers and melons w e recommend the greenhouse be located in a north south direction and for those to...

Page 3: ...ps head Screwdriver for recessed head screws siz e 2 1 pc O pen jaw wrench 10 mm 0 4 1 pc Screwdriver for slotted screws 1 pc W ater level 1 pc Step L adder approx 6 feet high 1 pc File to remove possible sharp edges 1 pc Rubber Mallet 1 pc Measuring Tape 1 pc E lectric or Cordless D rill 1 pc Bungee Cord 1 pc Caulking Gun IN D E X Part L ist Pages 4 5 Main Frame Assembly Pages 6 11 Foundation Fra...

Page 4: ...rossbar 2x 1 8 Roof Window Crossbar RIGA IV IV s 2x 1x 1 9 Rear Wall Middle Crossbar 1x 2 0 Lateral Supports 4x 2 1 Curved Corner Profiles with 1 channel 4x Detail A Floor Profile page 7 Detail B Front Crossbar Connection page 8 Detail C Window Door Hinge page 16 Detail D Window Door Frame connection page6 Detail E Roof Beam Connection page 7 2 2 Curved Center Profiles with 2 channels II 2x III 4x...

Page 5: ...4 6 6 1 2 1 1 1 1 1 1 2 2 4 4 12 12 8 8 1 1 16 16 6 6 1 1 24 24 4 4 21 feet 27 feet 1 1 1 1 1 1 6 6 3 3 24 feet 24 feet M6 M6 x 30 30 x 10 x 4 60 x 27 2 x7 4 40 x 40 x 4 50 x 50 x 5 95 Ø 35 x M6 40 x 30 x 30 4 2 x 13 4 8 x 45 Ø 10 3 5 x 16 4 8 x 25 4 8 x 50 M6 x 20 M6 3 5 x 38 2mm 3 5 mm 6 8 mm 8 50 50 1 8 8 4 6 1 1 1 1 2 4 12 8 1 16 6 1 24 4 21 feet 1 1 1 6 3 24 feet 24 feet 15 feet wedge seal fi...

Page 6: ...their holes using sheet metal screws 3 5 x 13 once the front glazing panels have been installed Important Slide 1 hexagon bolt M6 x 16 down each door profile channel See Illustration 2 on left These are for the assembly of the Door Frame Cross bars at the top III 2 M6 x 16 v ie w fr o m th e fr o n t holes for sheet m etal screw 3 5 x13 Step 2 Rear Window Frame Assembly Repeat everything in Step 1...

Page 7: ... on a stepladder Step 9 Adding additional Curved Center Profiles 2 2 Now add more Curved Center Profiles as necessary Series II uses only 1 on each side III uses 2 on each side and IV uses 3 on each side Slide each along the Side Floor Profile as well as the Roof Beam at the same time Be careful to move the profile only inches at a time on each end Preferably one person pushes at the bottom while ...

Page 8: ...ther side of the greenhouse Once completed you have installed one section of Glazing Panel on each side Step 11 Placing the Roof Window s In order to continue placing the Roof Glazing Panels you must decide on which side you want your Roof Window s This might depend on the prevailing wind It is best not to put Roof Windows facing a prevailing wind but put them on the otherside of the greenhouse Ho...

Page 9: ...an set the Front Crossbars 1 4 on top of the bottom Glazing Panels Then place on top of each Crossbar a Glazing Panel with the curved edges making sure the side with the UV filter in facing outwards as always Now permanently attach the Crossbars to the outersupports Curved Corner Profiles and Door Frame using screws 4 8 x 45mm 0 2 x 1 75 See picture on the left Next insert the small triangular Gla...

Page 10: ...iece Place one bolt near the center and one at each end Choice 1 At the beginning Mount the Foundation Frame by hooking it into the floor profiles 1 1 and 1 2 before you start to assemble the RIGA greenhouse Many prefer this method Special L brackets have been provided for you to do it this way You slide a Hexagon Bolt into the center channel towards the middle of each of the 4 Foundation Frame se...

Page 11: ...he greenhouse on top of a deck concrete slab or a specially build low wall just to add 6 more of head room Attach either the Foundation Frame or Floor Profiles to your foundation using appropriate screws or bolts Recommendation Place at least 1 screw bolt every 3 feet diameter 0 3 0 4 Notice There are no pre drilled holes in either the Floor Profiles or the Foundation Frame for mounting to a hard ...

Page 12: ... to insert 2 Hexagon Bolts M 6x16 into one of the Skylight profiles 5 0 This one will become the bottom of the window as these will be later used to attach the Automatic Window Opener Attention In order for the window to be able to close correctly you must make sure that the 2 ends with a slight cut out of each of the vertical side profiles are facing to the top Look carefully at each end and put ...

Page 13: ... corner connector 1 2 x 1 2 x 0 4 4 4 2 Vertical Window Support without holes 50 7 4 3 Horizontal Window Frame Supports 30 1 2 4 4 Vertical Window Support with holes for hinges 50 7 1 Y seal 15 feet Part of the Total Parts List Pos 4 2 Pos 4 4 Mounting of the skylight roof window Slide the narrow circular channel sticking out of the top Skylight Profile 5 0 of the fully assembled roof window see I...

Page 14: ...ts After they are lined up the profiles are screwed together with the screws going through the screw channels in the Top Crossbar 2 1 Use the sheet metal screw 3 5 x 32 0 15 x 1 25 See Picture Next place the large Lower Crossbeam 4 wide with doorhandle hole 2 4 and screw it together with the sheet metal screws 4 8 x 50 0 2 x 2 Two screws each go on both sides as shown Lower Door Section See Ill 2 ...

Page 15: ...l on the outside of the profiles with the lip pointing to the inside See illustration at bottom of last page and above Next Insert the Glazing Panels into both door sections on the inside and push in place the GHD seal as shown on the left Ill 1 on this page Door glazing door rung Seal 2 mm Door Handle Assembly Instructions Ill 1 Ill 2 ...

Page 16: ...tal bracket with the treaded pin sticking up to the Rear Wall Crossbar under the window to the Hexagon Bolt placed there earlier By trial and error determine the optimal position you desire for both ends of the Manual Window Opener Hold the window in a fixed open position by placing any eye in the handle bar over the pin sticking up from the Crossbar below the window and holding it in place with t...

Page 17: ... screws 3 5x19 Hold the parts is place mark the screw locations with a pen and then drill your own holes Inserting the Rubber Seals 1 On the inside Wedge the narrower seal 3 5 mm as shown pull apart if necessary between the Front Back Wall Glazing Panels and the Floor Profiles see illustration on left This should require little or no strength just push it in place with 2 or 3 fingers 2 On the insi...

Page 18: ...l Supports against the wall of the greenhouse as you have Curved Profiles i e RIGA III has 4 Curved Profiles on each side Attach to each bolt the longer flat end 1 25 of the Cross Struts about 16 long and secure with nuts Next Bend the cross struts to a horizontal position Ill 2 Then Slide into the bottom and side channels of another Lateral Support similar to the one already fixed into the wall o...

Page 19: ...teral Support which is placed against the greenhouse side wall as you have Cross struts You should have received an extra cross strut for each glazing section place half way between Curved Profiles Insert the same amount of bolts on the bottom channel of the other Lateral Support In addition slide as many Hexagon Bolts as you have chains hanging down into the channel on the front side of the secon...

Page 20: ... 3 Your RIGA greenhouse should be ventilated as much as possible especially when condensation develops However high humidity is preferred by some plants and especially during the seed to seedling stage Have lots of fun and success with your RIGA greenhouse from Hoklartherm enjoy the fruits of your labor Please contact your supplier for information about Special Accessories for your RIGA greenhouse...

Reviews: