9 Installation of the boiler
Dear Professional, Smart Fire
boiler
is a highly efficient high technology system. Therefore we
plead for careful and thoughtful work with installation.
Only persons holding necessary licences, knowledge, skills and equipment can be trusted with
assembly of the boiler. Launch, periodic maintenance and repairs can only be performed by the
authorised service professionals who had been trained adequately.
Always submit to all applicable national and European standards and other local regulations that
might apply, when installing
boiler
s.
9.1 Transport of the boiler into the building
Apply outmost care when transporting the boiler. Watch for the electronic devices and cables. If you
cannot avoid dismantling of an obstructive piece, remember how it was attached, make notes and a
photo when necessary. This way you will be able to assemble the unit and assist the service if its
involvement proves necessary.
9.2 Boiler room – placement of the boiler
The room where the boiler is installed must satisfy the applicable regulations and standards
concerning solid fuel boilers. In particular, pay attention to safety of the water and electricity
installations, adequate ventilation, exhaust system and fire safety. The boiler room must be airtight,
with adequate ventilation and air supply, separated from other rooms with permanent walls and
airtight doors preventing eventual spreading of smoke, particularly rooms where there are people.
Assure the mandatory clearance from walls and other items:
•
min, 1200 mm in front;
•
min. 1000 mm at the fuel container side;
•
min, 500 mm at the boiler's side;
•
min. 500 mm - back;
•
min. 800 mm above.
A sketch of Smart Fire placement in the boiler's room showing the necessary clearances is shown at
the fig. 10.
Smart Fire Manual
wer. 05/07/2012/EN/SL V2.0
HKS LAZAR
str.24
Summary of Contents for SF 21
Page 36: ...13 Declarations and licensing Smart Fire Manual wer 05 07 2012 EN SL V2 0 HKS LAZAR str 36 ...
Page 37: ...Smart Fire Manual wer 05 07 2012 EN SL V2 0 HKS LAZAR str 37 ...
Page 38: ...Smart Fire Manual wer 05 07 2012 EN SL V2 0 HKS LAZAR str 38 ...
Page 39: ...Smart Fire Manual wer 05 07 2012 EN SL V2 0 HKS LAZAR str 39 ...
Page 40: ...Smart Fire Manual wer 05 07 2012 EN SL V2 0 HKS LAZAR str 40 ...