31
────────────────────────────────────────────────────
5.3 Standard Commands
────────────────────────────────────────────────────
Voltage or resistance indicator (unit)
Resistance
Test time enablement
ON
Maximum test value enablement
ON
Minimum test value enablement
OFF
Output current value
25.0 A
Maximum test value (resistance)
0.100
Ω
Minimum test value (resistance)
0.000
Ω
Maximum test value (voltage)
2.50
Ω
Minimum test value (voltage)
0.00
Ω
Test time
60.0 s
*
OPC
■
After all action has been completed during execution, performs an SRQ request.
*
OPC?
■
Queries whether or not all action has been completed during execution.
*
RST
■
Performs device initial setting.
Syntax
*
OPC
Function
Sets bit 0 (the OPC bit) of the standard event status register (SESR) to 1 at
the instant the previous commands which is on the same line with *OPC
have been completed.
Error
If the data parameters are set after this command, a command error occurs.
Syntax
*
OPC?
Function
・
The same as the *OPC command, except in that, at the instant that the
previous commands have been completed.
・
Returns the response message "1", instead of bit 0 (the OPC bit) of the
standard event status register (SESR) being set to 1.
・
No header is affixed to the response message.
Error
If the response message is longer than 300 bytes, a query error is generated.
Syntax
*
RST
Function
Resets the 3157. The items which are reset are listed below.
Error
If the data parameters are set after this command, a command error occurs.
Summary of Contents for 9518-02
Page 1: ...GP IB INTERFACE INSTRUCTION MANUAL 9518 02 3157 AC GROUNDING HiTESTER...
Page 2: ......
Page 6: ...ii Introduction...
Page 74: ...68 5 6 Initialization Items...
Page 84: ...78...