GST-IFP4M Intelligent Fire Alarm Control Panel
Installation and Operation Manual
Page
12
2
Installation
This chapter describes the installation of the FACP.
The steps below are guidance for
installation of the FACP.
1
Check if you have received all items ordered.
2
Install the cabinet.
3
Install the component (basic and optional).
4
Power up the FACP and check if it can be normally started.
5
External connection.
6
Check the lines.
7
Setup FACP and define devices using GST-IFPx-Def Defining Tool on a PC and
download them to the FACP according to engineering configuration.
8
Check and commission peripheral devices.
2.1 Component Inspection
Before installation, check the following items:
Check Engineering Requirement
Check the packing list according to engineering requirement. The main items to be
examined are: installation and operation manual, key to the FACP, battery wires, terminal
resistor and etc.
Check Internal Components and Interconnection inside the FACP
All basic internal parts have been connected (including power supply box, mother board,
main board, interface board and main front panel) before the FACP leaves the factory.
Therefore, you can mainly check the optional units ordered and the connection among
parts, including the connection between mother board and power supply, mother board
and key board, the connection of the zone indication panel with key board, etc. Please
refer to Appendix A for the internal connection diagram.
2.2 Install the Cabinet
2.2.1 Install the cabinet of panel
The cabinet mounts using three 12mm-diameter holes located in the back box. Carefully
unpack the system and check for shipping damage. Mount the cabinet in a clean, dry,
vibration-free area where extreme temperatures are not encountered. The area should be
readily accessible with sufficient room to easily install and maintain the panel. Locate the
cabinet at a proper height above the floor with the hinge mounting on the left.
The FACP can be flush-mounted or wall-mounted. The dimensions for wall-mounting are
shown in following Fig 2.1
Mark and predrill holes in the wall for the three keyhole mounting bolts using the