9
Revision date: 04.17.20
2-Layer Film Install
Mark Ribbon Board Location
Ribbon board runs along each frame side and serves as a mounting surface for side u-channel.
Ribbon board is required for greenhouses that include
roll-up sides.
Read through the information on this page and continue as instructed. Customer is responsible for supplying materials to construct a ribbon board (and
baseboard if used) as described. Fasteners to secure ribbon boards (and baseboards) to frame are included. See ribbon board information earlier in this
guide.
Complete these steps:
1. Using diagrams included in frame assembly
Guide #1
, mark ribbon board location on frame along each side at each end rafter.
NOTE:
When side panel is rolled up, sidewall opening is
typically 48" to 54"
depending on intended use and building size.
Do not exceed 54".
2. Stretch a chalk line from end to end, verify it is level, and snap to mark
top of ribbon board
on each rafter tube along each side.
3. Continue by installing ribbon board and baseboard as described on next page.
Ribbon Board
Baseboard
Top of Ribbon
Board
Maximum
opening is 54"
from bottom of
ribbon board.
Ground Level