14
2-Layer Film Install
Revision date: 04.17.20
2-Layer Film Roof — Layer 1 (IR/AC)
INSTALL IR/AC FILM COVER
Continue with the following procedure.
Greenhouse includes two film types. Install the IR/AC
film first!
Gather parts:
• Cover film and wire spring (#102198A)
• Ropes/straps long enough to reach over frame
(provided by customer)
After attaching 102197 u-channel along sides and u-channel flashing to end rafters, install IR/AC
cover film. Ropes or straps are typically used to pull main cover onto and over the frame.
Complete these steps:
1. Take film and position it along base at one side. Ensure IR/AC cover will pull over frame with correct surface positioned toward the soil.
NOTE:
Unfold cover and locate edge. Cover ground if needed to protect film and to keep film clean and free of debris.
WARNING:
To prevent damage
to the cover and to prevent
serious personal injury,
DO
NOT
attempt to install the main
cover on windy or stormy days.
WEAR EYE
PROTECTION
WHEN
INSTALLING
SPRING WIRE!
DOUBLE-LAYER FILM INSTALLATION
Greenhouses equipped with a double-layer film include a layer that is Infra Red (IR) Retention film; item 109094, 109095, 109096, 109097, or 109098.
During cover installation, install IR/AC film first! Examine film and install it according to instructions printed on film.
Actual frame may differ
from example shown.
ATTENTION:
Depending on greenhouse
size, the roll-up side panels may be part
of the main cover, or they may be an
individual panel cut from a separate roll
of film.
Main cover film is typically cut two (2)
feet longer than greenhouse (e.g., length
is 48'; film roll is 50'). When choosing
the correct film roll for cover, review
documents included with shipment to
identify the film. Roll out along frame and
measure.
Also, ensure you have selected the IR/AC
film for your first layer.
Install this film
first and according to the instructions
printed on film.