background image

15

Revision date: 04.17.20   

2-Layer Film Install

IMPORTANT:

 To prevent damage 

to cover film during installation, 

use 

additional personnel and lifts as 

needed stationed inside frame

.

4.  Center side-to-side and end-to-end.  

 

NOTE — ROLL-UP PANELS:

 For 

small frames, roll-up panel is part of 

roof film. It is important to center cover 

on frame so each side has an equal 

amount of film hanging below ribbon 

boards 

before securing film to 

u-channel

. Do not cut this film off! 

It 

is the roll-up portion of cover.

5.  Once main cover is in place and 

centered, begin at peak at one end 

and install the 102198A wire spring 

into the 102197 u-channel. 

 

ATTENTION: 

Ensure enough film is 

present to lock into u-channel flashing. 

Typically, cover film is cut longer 

than required to cover frame end-

to-end. For easier anchoring, allow 

approximately 10" to extend past end 

rafter as film is anchored. Remove 

ropes (if used) after film is secure. 

6.  Continue down both edges of first end 

rafter until film is secured. 

7.  Pull film toward other end and stretch 

gently to remove wrinkles.

2.  Along film edge to pull over frame, tie rope (or strap) around a tennis ball, for example, and 

toss free end of 

rope over frame

. See photo. Not required for small greenhouses; pull cover over by hand when possible.

 

 

NOTE:

 Evenly space ropes along side. Number of ropes depends on building length; use additional ropes 

spaced evenly throughout length to prevent tearing cover when pulled onto frame.

3.  After tying ropes to cover, 

throw free end of each rope over building

 and pull cover onto frame. 

INSTALL COVER FILM (continued)

WEAR EYE 

PROTECTION 

WHEN 

INSTALLING 

SPRING WIRE!

Step 3

Step 5-7

2-Layer Film Roof — Layer 1 (IR/AC)

Summary of Contents for PGFLSAXXFCW0063

Page 1: ...ssion Photo may show a different but similar model Greenhouse with single door and roll up sides is shown in the example 2 Flashing Ribbon Board Baseboard 102197 U Channel Install Film Layer 1 Air Inf...

Page 2: ...to prevent entrapment Important Information Contents Important Information 2 Required Lumber Customer Supplied Ribbon Boards 4 Recommended Customer Supplied Baseboards 5 End Panel Installation Detail...

Page 3: ...ers for wire spring 1 4 or 5 16 drill bit 1 3 8 hole saw bit Hand tools saw or grinder to cut aluminum flashing Clamps to install u channel flashing Ladders work platforms and other machinery for lift...

Page 4: ...sult main frame technical document to determine ribbon board height for your greenhouse ATTENTION Fasteners to secure boards to building frame are included with building materials Minimum lumber dimen...

Page 5: ...oards run the frame length along both sides at ground level Installation of customer supplied baseboard is described later in this guide Do not install boards at this time ATTENTION Fasteners to secur...

Page 6: ...r Apply foil tape DH8007 to cover all open cells after cutting and before flashing if this has not been completed yet U channel flashing overlaps end panels to cover open cells at top If end panels ar...

Page 7: ...re rafter begins to bend Place flashing on ground or work bench 3 From first cut mark remainder of flashing face at 12 on center intervals Flashing PGFLSAXXFCW0063 Installation ATTENTION To bend flash...

Page 8: ...ed Use hand clamps to help hold and bend flashing into position 9 Continue installing flashing and work down to ground INSTALL FLASHING CONTINUED Flashing 6 7 Flashing ATTENTION Be mindful of where to...

Page 9: ...frame are included See ribbon board information earlier in this guide Complete these steps 1 Using diagrams included in frame assembly Guide 1 mark ribbon board location on frame along each side at e...

Page 10: ...nuts Review diagram below INSTALL RIBBON BOARDS 1 After flashing is installed attach ribbon boards to assembled frame Use a drill and 5 16 drill bit to drill through rafter tubes and ribbon board Secu...

Page 11: ...u channel using FA4482B Tek screws NOTE Align u channel with center of end rafter and install over and through the installed flashing 2 Continue to install u channel up and over the end rafter down to...

Page 12: ...wood screws 2 Continue attaching u channel and work toward other end of frame U channel to run level throughout installation 3 Cut last section to required length so it is flush with outside edge of...

Page 13: ...rn to rafters and apply tape over connectors to better protect cover film and prolong film life once installed Photo above shows one way to apply the tape Rafter and frame shown above may differ from...

Page 14: ...to prevent serious personal injury DO NOT attempt to install the main cover on windy or stormy days WEAR EYE PROTECTION WHEN INSTALLING SPRING WIRE DOUBLE LAYER FILM INSTALLATION Greenhouses equipped...

Page 15: ...nger than required to cover frame end to end For easier anchoring allow approximately 10 to extend past end rafter as film is anchored Remove ropes if used after film is secure 6 Continue down both ed...

Page 16: ...the side Use upper run of u channel to secure roof film if two 2 runs of channel are attached to ribbon board 10 Next move to remaining side stretch film and secure in place Pull film sung during spri...

Page 17: ...the example Some larger buildings may include multiple inflation fan kits ATTENTION Install all air inflation fan kit components before installing the second layer of film Failure to do so will requir...

Page 18: ...Lower run of u channel is reserved for roll up side panel ATTENTION Install second layer of film with either surface toward the soil Do not damage first film layer during installation of second film 2...

Page 19: ...Greenhouse Anytime after roof film installation apply sealant to these areas Around all doors Around accessory framing and accessories At joint where u channel meets flashing for both end rafters All...

Reviews: