DC Inverter Multi
VRF Service Manual
91
3 INSTALLATION OF OUTDOOR UNIT
3�1 Hoisting of Unit
Transport the unit to a place as close as possible to the installing site before taking it out of the packaging box.
CAUTIONS!
Never put any object on top of the unit before and after installation.
To lift the machine with crane, please use two ropes to lift the outdoor unit.
Hoisting Method
The machine must be balanced when it is lifted. Check and ensure that the machine can be lifted up safely and stably.
CAUTIONS!
Do not attach the ropes to the lower wood frame of the packaging box.
Never remove any packaging materials.
As shown, insert two ropes through the square holes on the machine and protect the machine with batten and
corrugated paper.
Less than
Never remove the wood
frame and plastic straps.
Rope
The angle between rope and
machine shall be higher
than 60º.
Tie the ropes the batten and
corrugated paper with a
thickness not over 15mm.
Do not apply any force to
this board (both sides).
Insert the ropes through
square hole.
During lifting, the position of ropes is as shown below.
Move the lower wood frame of the packaging box away and lift the unit to correct position.
Rope
Square hole
Rope
Square hole
Correct
Correct
Summary of Contents for CN851W1000
Page 1: ...DCINVERTERMULTIVRFSERVICEMANUAL T1 R410A 50Hz GC201107 CENTRAL AIR CONDITIONERS ...
Page 6: ...DC Inverter Multi VRF Service Manual 1 PRODUCT PRODUCT ...
Page 24: ...DC Inverter Multi VRF Service Manual 19 CONTROL CONTROL ...
Page 92: ...DC Inverter Multi VRF Service Manual 87 INSTALLATION ...
Page 146: ...DC Inverter Multi VRF Service Manual 141 ENGINEERING DEBUGGING ...
Page 171: ...166 DC Inverter Multi VRF Service Manual MAINTENANCE ...
Page 233: ...JF00300207 ...