Butt fusion preparation
The machine can be prepared for butt fusion in only a few steps.
Loosen the knurled-head screw. Pressure is now built up via spring tension.
The groove in both eccentric screws (in front and at the back) should be
horizontal and secured with the safety screw. The heating plate can be moved
axially