C
GFK-2734
Chapter C Planning
C-3
No. Requirement (optional)
Yes
No
Remark
18
Have specifications for assembly and electrical installation been de-
fined (e.g., EPLAN) and communicated to the relevant personnel?
19
Have the separate voltage areas been taken into account?
20
Have specifications for the safety-related segment circuit been taken
into account (jumpers, approved terminals, fuse protection)?
21
Have specifications for startup been defined and communicated to the
relevant personnel?
Date
Signature (author)
Date
Signature (test engineer)