9–2
PQM POWER QUALITY METER – INSTRUCTION MANUAL
COMMISSIONING
CHAPTER 9: COMMISSIONING
COM 2 RS485 PORT
COM 2 BAUD RATE
baud
COM 2 PARITY
FRONT PANEL RS232 PORT
RS232 BAUD RATE
baud
RS232 PARITY
DNP 3.0 CONFIGURATION
DNP PORT
DNP SLAVE ADDRESS
DNP TURNAROUND TIME
ms
CLOCK
SET TIME hh:mm:ss
SET TIME mm:dd:yyyy
CALCULATION PARAMETERS
EXTRACT FUNDAMENTAL
CURRENT DEMAND TYPE
CURRENT DEMAND TIME INTERVAL
min.
POWER DEMAND TYPE
S1 PQM SETUP continued
POWER DEMAND TIME INTERVAL
min.
ENERGY COST PER kWh
cents
TARIFF PERIOD 1 START TIME
min.
TARIFF PERIOD 1 COST PER kWh
cents
TARIFF PERIOD 2 START TIME
min.
TARIFF PERIOD 2 COST PER kWh
cents
TARIFF PERIOD 3 START TIME
min.
TARIFF PERIOD 3 COST PER kWh
cents
EVENT RECORDER
EVENT RECORDER OPERATION
TRACE MEMORY
TRACE MEMORY USAGE
cycles
TRACE MEMORY TRIGGER MODE
Table 9–1: PQM Setpoints (Sheet 2 of 12)