Press the red commissioning button located next to the inverter
and mode switch. (note-there should not be a present input on
the open terminal from field wiring, this will prohibit the gate
from closing, a momentary pulse is all that is required).
Ensure the direction the gate first travels is toward the fully open
position, if the gate first travels towards the closed position then
turn the power off and reverse two of the motor wires at the
inverter terminals.
For the commissioning process the gate will fully open, then 2
seconds later it will automatically fully close. During this
commissioning the PE beam and Door inputs are not required.
Once the gate is commissioned (gate has fully closed) the gate
distance is in the memory of the inverter, the Door and PE beam
inputs need to be connected.
Give a pulse input to the open terminal and the gate will open
(note. The gate will perform one slow speed operation to
confirm the gate opening distance and will then be ready to run
at full speed).
Select desired mode of operation via the thumb wheel selector
switch (please refer to the installation manual for mode functions).
If inverter settings require adjusting for example Opening,
closing speeds, ramp times etc. please refer to the installation
manual for instructions and parameter description list.