MDE-4813D CFN PLUS Installation Manual · February 2018
21
•
Grounding
o
At least 10 mm
2
Grounding cable to pump chassis
o
At least 10 mm
2
Grounding cable to CFN PLUS pole
o
Grounding cable to TLG - in accordance with TLG manufacturer
instructions.
•
Tank conduit
o
TLG probe
2-4.5. Wiring conduits in CFN PLUS
CFN PLUS includes four wiring openings, each carrying specific wires, as listed in
Table 2-1. Conduits into CFN PLUS
No.
Conduit Type
Type
1
Low voltage
Pulser, TLG, LAN
2
Low voltage
Barrier
3
High voltage
AC power, GND, control
4
High voltage
In-use
2
2
-
-
5
5
.
.
C
C
O
O
N
N
D
D
U
U
I
I
T
T
S
S
I
I
N
N
S
S
T
T
A
A
L
L
L
L
A
A
T
T
I
I
O
O
N
N
2-5.1. General
This paragraph describes the infrastructure groundwork necessary to install the conduits in the
station (see
2-5.2. Installing Conduits in Station
Proceed as follows:
1.
Determine the location of the CFN PLUS in the station.
2.
Dig and prepare passageways for the necessary conduits
3.
Route the following conduits to the inspection boxes:
•
Low voltage cables inspection box:
o
One conduit to Office (control room)
o
One conduit to each pump
o
Two conduits to CFN PLUS
•
High voltage cables inspection box:
o
One conduit to Office (control room)
o
One conduit to each pump
o
Two conduits to CFN PLUS