Revision 4
90
August 02, 2019
8.3 QA Document Package Check List and Requirements
Table 8-1 is completed during the manufacturing process and QA inspection to ensure that
the all relevant operations are performed.
Table 8-1: Document Package Check List
Serial Number: _______________
Description
Initial
Date
Sample System Pressure Checked - System Heaters
Sample System Pressure Checked – Sample System
Purge System Checked
Aspirator Performance Tested
Gas Runs Complete (Calibration Data Sheet)
Temperature Sensor Inputs Checked and Calibrated
Analog Output Calibration Checked
Digital Output Checked
System 24VDC Supply Checked
Span Factor Set
Condenser Solenoid Function Checked
Zero Solenoid Function Checked
Control Cabinet Air Solenoid Function Checked
Operation of Cell Heaters Checked
Burn Oven for three (3) weeks
Cell Pressure Transducer Checked.
Dielectric Strength Test Certificate Completed
Matrix and Cal Documents Completed
Serial Numbers Recorded
Oven Lid Latches Adjusted and Locked
Summary of Contents for 943-TGX
Page 48: ...Revision 4 48 August 02 2019 Figure 4 13 Network Sub Panel...
Page 94: ...Revision 4 94 August 02 2019 Figure 9 3 Control Cabinet Detail...
Page 96: ...Revision 4 96 August 02 2019 Figure 9 5 AC Wiring Diagram...
Page 97: ...Revision 4 97 August 02 2019 Figure 9 6 DC Signal and Wiring Diagram...
Page 98: ...Revision 4 98 August 02 2019 This Page Intentionally Blank...