Transitioning
from backup
power mode to
feeding energy
into the grid
1.
The inverter is operating in backup power mode. The contactors K1 and K2 to the
public grid are open.
2.
Public grid available again.
3.
The Fronius Smart Meter monitors the grid parameters on the public grid and
passes this information to the inverter.
4.
The stability of the returned public grid is determined by checking the measured val-
ues of the Fronius Smart Meter.
5.
On the basis of adjustments that have been carried out, the inverter ends backup
power mode and disconnects the outputs.
6.
The inverter deactivates K3 and K6. Power is restored to contactors K1, K2, K4 and
K5.
7.
All circuits are reconnected to the public grid and are supplied by the grid. The
inverter does not feed anything into the grid at this time.
8.
The inverter can start feeding energy into the grid again after performing the grid
checks required by the relevant standard.
40
Summary of Contents for Symo GEN24 10.0
Page 2: ......
Page 10: ...10 ...
Page 11: ...General information 11 ...
Page 12: ...12 ...
Page 28: ...28 ...
Page 29: ...Backup power variant PV Point OP 29 ...
Page 30: ...30 ...
Page 32: ...32 ...
Page 33: ...Backup power variant Full Backup 33 ...
Page 34: ...34 ...
Page 41: ...Installation 41 ...
Page 42: ...42 ...
Page 82: ...82 ...
Page 83: ...Settings web interface of the inverter 83 ...
Page 84: ...84 ...
Page 104: ...104 ...
Page 105: ...Appendix 105 ...
Page 106: ...106 ...
Page 116: ...116 ...
Page 117: ...Circuit diagrams 117 ...