INSTALLATION
Models 60" through 96"
Basin Height
“H”
Min. Hole Depth
“D”
60" (152 cm)
64.5" (163.8 cm)
72" (183 cm)
76.5" (194.3 cm)
84" (213 cm)
88.5" (224.8 cm)
94" (239 cm)
98.5" (250.2 cm)
Item No.
Description
1
Compact gravel bedding material, minimum 6' depth
2
Clean compactible backfill
3
Concrete ballast, poured by contractor
4
Clean compactible backfill
5
4" intake plumbing (not provided, shown for reference only)
6
2" screened mushroom vent cap
(Vent plumbing not provided, shown for reference only)
7
1-1/4" SHC 80 PVC spigot tank discharge connection.
8
48" flexible discharge connection 1-1/4" PVC socket or 2” PVC spigot
9
Redundant check valve (not provided, shown for reference only)
10
Stop valve (not provided, shown for reference)
11
Force main or gravity line
12
Pump power and/or control, float control direct bury cable or continuous conduit
(not provided, shown for reference)
Leave 6"–12" coil of excess cable to allow ground settling or shifting
13
Conduit (not provided, shown for reference)
14
Control panel
15
Property service control panel connection (not provided, shown for reference)
16
Adjacent structure, fountain footing or property line
14
13
12
16
1
2
3
4
5
6
7
8
9
10
11
Slope Grade Away from Basin
Basin Rim 1.5" Above Grade
Direct Bury Cable
24" Minimum Below Grade
4" Min. Over Integral
Anti-Flotation Flange
Basin Height
See Table, “H”
8" Concrete
Ballast
6" Mimimum Compacted Gravel Bedding
84" Min.
45
°
Min.
36" Min.
53"
Min. Hole Depth
“D”
15