Commissioning
It is recommended that the following safety measures are taken before starting up the facility for
the first time, or after a trip event:
•
Once all of the connections have been made, we recommend a check to make sure that
they are correct, safe and well attached.
•
The "complete test" menu procedure should be applied.
NOTE! See 5.10.
•
It is important to check that the measurements are correct once the facility has been
powered up.
Maintenance
:
FANOX recommends a minimum of one facility inspection per year, to at least go
through the test menu and check the values of the measurements.
Summary of Contents for SIA-F
Page 7: ...www fanox com Rev 17 7 119 2 DIMENSIONS AND CONNECTION DIAGRAMS 2 1 Frontal view...
Page 8: ...www fanox com Rev 17 8 119 2 2 Case dimensions The dimensions are in mm CUT OUT PATTERN...
Page 9: ...www fanox com Rev 17 9 119 2 3 Connection diagram 3 Phase CT and neutral CT Connection...
Page 10: ...www fanox com Rev 17 10 119 3 Phase CT and residual neutral Connection...
Page 34: ...www fanox com Rev 17 34 119...
Page 35: ...www fanox com Rev 17 35 119...
Page 36: ...www fanox com Rev 17 36 119...
Page 118: ...www fanox com Rev 17 118 119 NOTES...
Page 119: ...www fanox com Rev 17 119 119...