Installing an Extension Arm 

 
Some gate installations do not meet the geometrical 
constraints shown in Figure 2. In those situations, the 
750 Extension Arm option can be used along with the 
750 drive unit, power unit, and control panel to install 
an unobtrusive gate operator. 
 
Using the 750 Extension Arm means that you do not 
have to permanently remove any leaf hinges, the gate 
leaf does not need to form a 90-deg angle on the bottom 
corner nearest the gate post, and the relative location of 
the rotation axis is not so restricted. 
 
The geometrical constraint for using the 750 Extension 
Arm is that the center of the splined shaft on the drive 
unit 

must

 be within 6 in. (15.25 cm) of the axis of 

rotation of the gate leaf. 

WARNING! 

 The farther away the splined 

shaft is from the gate's axis of rotation, the 
greater the risk of danger from pinch points.  

Install the drive unit so that the splined shaft is as near 
as possible to the gate's rotation axis and is directly 
beneath the center of the fully closed gate leaf. 
 
You need to position the extension  collar (see Figure 
23) so that it smoothly slides within the extension U 
from the fully closed to the fully opened position. Note 

that the position of the extension collar is affected by 
the overlap of the extension bar and extension U. 
 
Attach the 750 extension collar to the bottom of the gate 
leaf with a 7/16 in. (1.1 cm) bolt. 
 
Weld together the extension bar and extension U 
according to Figure 23. 

Caution:

 Do not weld anything to or on the 

inside of the sleeve of the splined shaft. 

Next, weld the outside of the sleeve for the splined shaft 
solidly to the inside of the hole in the end of the 
extension bar.  
 
Follow the rest of the instructions for installing the 750 
Operator. With an extension arm, you need not worry 
about installing a gate leaf shoe nor about installing the 
gate leaf in the shoe.  Instead, you will install one end of 
the welded extension arm over the splined shaft and the 
other end around the extension collar.  
 
In addition, you will need to provide a washer  beneath 
the extension collar to keep the extension U from falling 
off the collar. You also need to shield any pinch points 
around the extension arm.  

(b) 

(a) 

Minimum overlap of 
2 1/2 in. (6.4 cm)

750 extension 
bar

750 extension U

750 extension 
collar is attached 
to the bottom of 
the gate leaf

Extension bar

Minimum overlap of  
 2 1/2 in. ( 6.4 cm) 

Extension U

Extension 
collar slides 
within 
extension U

Hole in the extension bar fits around and 
is welded to the outside of the sleeve of 
the splined shaft 

Bottom of 
gate leaf

 

Figure 23. The 750 Extension Arm, (a) side view and (b) top view 

Summary of Contents for 750 Standard

Page 1: ...the Drive Unit 12 Connect the Hydraulic Lines 12 Synchronize the Hydraulic System 13 Install the Gate Leaf Shoe 13 Install the Gate Leaf 15 Installing the Control Panel 15 Connect the Main Power Supp...

Page 2: ...ortant that you locate the gate far enough away from the road to eliminate the potential of traffic getting backed up This distance is affected by the size of the gate how often it is used and how fas...

Page 3: ...ipment observe some fundamental rules Do not touch the equipment with damp or humid hands or feet Do not install or operate the equipment with bare feet Do not allow small children or incapable person...

Page 4: ...cluding shaft length width in cm 47 8 153 4 77 8 12 4 40 20 Weight 100 deg swing lb kg 180 deg swing lb kg 18 8 20 9 Oil quantity qt l 0 9 1 Maximum angle of rotation 100 deg swing deg 180 deg swing d...

Page 5: ...ts base plate with 4 leveling bolts installed and with the sleeve fitted over the splined shaft 2 Box halves right angled and lipped pieces of galvanized steel that together form the sides of the box...

Page 6: ...isengaged you can open and close the gate leaf by hand Such manual operation of the gate is necessary during installation and useful during power failures The two bypass valves are located on the fron...

Page 7: ...them after pause time Opens single leaf connected to Motor 1 and closes it after pause time No effect No effect No effect Off Opening Closes both leaves immediately Closes the leaf immediately Stops S...

Page 8: ...1 No effect opening is inhibited No effect opening is inhibited No effect opening is inhibited Off Opening Stops Stops Stops Stops gate closes when reversing device no longer triggered No effect On O...

Page 9: ...50 Operator consists of the following steps Setting the concrete forms Installing the power unit Installing the drive unit Connecting the hydraulic lines Synchronizing the hydraulic system Installing...

Page 10: ...x 18 in 25 4 x 45 7 cm Axis of rotation of gate leaf Gate post Minimum of 2 1 4 in 5 7 cm maximum of 5 1 4 in 13 3 cm One of 4 bolts that anchor plate into cement footing Figure 4 Recommended dimensio...

Page 11: ...and then lift it off the box The vinyl hinges can now be placed in the hinge receptacles on the right hand side Secure the hinges with the screws provided You may surface mount the power unit box to...

Page 12: ...e the necessary holes for the two hydraulic lines that run from the drive unit to the power unit Once you have made your access holes you can weld the box halves to the foundation plate and to one ano...

Page 13: ...ruct a shear pin assembly to accommodate the extra vertical distance The assembly is welded to the bottom of the gate leaf shoe on one end and to the sleeve for the splined shaft of the pinion on the...

Page 14: ...he bottom side of the U shaped section of the shoe as shown in Figure 10 On the bottom of the U shaped shoe section center the sleeve around the pilot hole that marks the axis or rotation Accurately c...

Page 15: ...veling bolts on the base of the drive unit to correct any problems with the gate s travel Installing the Control Panel Locate the control panel in the most convenient position possible considering the...

Page 16: ...anel box C 3 X 18 AWG 3 X 18 AWG 4 Main power switch D 5 X 18 AWG 5 X 18 AWG 5 Circuit breaker E 5 X 18 AWG 5 X 18 AWG 6 Main junction box F 4 X 14 AWG up 3 X 14 AWG up 7 Switch for 750 Operator to 41...

Page 17: ...in block J1 and connect the power wires to the terminals labeled N neutral and L phase Caution The operators are grounded only by the grounded circuit the installer provides Connect One Activating Dev...

Page 18: ...ystem has one operator connect the capacitor and the brown and black or red and black wires from your operator to the terminals 3 and 5 in block J2 for Motor 1 Connect the blue or white wire from the...

Page 19: ...Panel U L Listed Control Panel Enclosure Cord grip or conduit from U L Listed gate operator s see text Ground Legend Red Black White Yellow Green a b J3 Figure 15 Wiring detail a inside the junction b...

Page 20: ...the motor s direction of rotation replace any test circuits you installed between terminals 11 and 13 between 13 and 21 and between 14 and 15 with the proper reversing and stop devices The instructio...

Page 21: ...J3 In addition terminal block J3 requires a fail safe connection for the photocells Connect the photocells to terminals 20 and 21 Activating Devices and Radio Receiver The acti vating devices and radi...

Page 22: ...y when an activating signal is sent for 2 and 1 gate leaves respectively DL3 should be illuminated except when the stop button is pressed DL4 and DL5 should be illuminated except when the reversing de...

Page 23: ...off EP on on off B on on on C off off on Switch 4 Reversing Device Behavior on Closing Refer to the operating logic tables later in these instructions and to the chart below for how to set DIP switch...

Page 24: ...unit through the bleed screw holes see Fig ure 18 You need to bleed the hydraulic system before setting the gate up for normal operation To run the gate leaf through an open close cycle make sure the...

Page 25: ...22 The location of the bleed screws on the drive unit top view WARNING The pressure the gate leaf applies to the obstruction is determined by the bypass valve adjustment It is the installer s respons...

Page 26: ...the extension collar is affected by the overlap of the extension bar and extension U Attach the 750 extension collar to the bottom of the gate leaf with a 7 16 in 1 1 cm bolt Weld together the extens...

Page 27: ...use check every 6 mo Check all reversing devices Every six months you should verify that all installed reversing devices work properly The Control Panel The control panel requires no maintenance Trou...

Page 28: ...a reversing device is triggered If either does not illuminate then one of your reversing devices is preventing the gate from responding to your signal Check your reversing devices If no reversing dev...

Page 29: ...use negligence or accident or has not been operated in accordance with FAAC International Inc s or FAAC S p A s instructions or has been operated under conditions more severe than or otherwise exceedi...

Reviews: