3722-IG-002 Installation and User Manual
February 6, 2019
12
Figure 7A
Installation
Recommended Mounting Method
Refer to the following table for a list of parts needed for installation that are not supplied as part of the EVSE unit. These
parts may be purchased at any reputable building supply store. Ensure that all parts meet or exceed local building codes for
quality.
Item
Qty.
Unistrut
2 sections (each 23 inches long min)
Simpson strong tie p/n DIA 375 or equivalent
4 min. or as required for use in concrete
¼” x 1” stainless bolts
4
¼” spring nuts
4
¾” electrical conduit
As required
Brackets and hardware to secure the conduit
As required
Wire (minimum wire size is #10, insulated copper. Wire size determined per
electrical code.)
As required
Removing the 3722 from the Shipping Box
Figure 7
1.
Place the box on a safe, flat surface and remove the top of the box.
2.
Lift the middle insert out (Figure 7).
3.
Lift one side of the unit up, remove the side foam framing and gently lower the unit back down. Repeat for the other
foam frame (Figure 7).
4.
Remove the charger from the box.
5.
Remove the two side screws from each side of the unit and lift the cover off. Place the cover and 4 screws in a safe
place (Figure 7). Remove the FOB, which is taped to the main plate underneath the Data Router (Figure 7A)
6.
Remove the four thread-forming screws and place them aside for future use (Figure 7A). Also, locate the bag
containing screws and washers for future use.
Figure 7A
FOB