there is sufficient cable length to strip and connect the cable to the wall dock. See
for cable connection instructions.
4.1.7. EV Ready certified connection (optional)
When an EV Ready certified connection is required, a shunt trip (for example, ABB type F2C-A2) must
be installed in the power supply cabinet.
Use cable with a wire diameter of between 1.5 and 2.5 mm
2
. Route the EV Ready cable from the MCB
and shunt trip in the power supply cabinet to the installation area of the charging station. Make sure
that there is sufficient cable length to strip and connect the cable to the charging station. See
for cable connection instructions.
EV Ready wiring diagram
Note:
A 3 phase installation is shown. A 1 phase installation is similar.
4.1.8. Implementation of VDE-AR-N 4100: 2019-04 (only for Germany)
All EVBox charging stations can be controlled directly by a distribution network operator (DSO).
Charging stations with a total rated power of more than 12 kVA must be controlled in accordance with
Technical Connection Rules VDE-AR-N 4100: 2019-04. A radio ripple control receiver enables the
charging station, which is located behind the specific DSO-controlled contactor, to be switched off
directly. The contactor must have the following technical specifications: 230 V AC, 40 A, 4 S and
nominal short-circuit current "Iq" 10 kA.
Registration with the local distribution network operator is required.
Example of a 4-pole contactor:
4. Installation instructions
EN
17