8.
Turn the tower cable around the
tower and fix it in the base. This will
avoid the noise of the cable hitting the
tower.
ATTENTION: Never leave the wind turbine without the tower cables connected in
the converter or short-circuited.
The wind turbine could start rotating without control.
In case power converter connection is carried out after wind turbine erection,
follow the steps:
1.
Remove one phase from the cable’s shortcircuit and connect to the X11
connector. Leave the other 2 phases short-circuited.
2.
Remove second phase from cable’s shortcircuit and connect to the X11
connector as fast as possible. During this operation, the wind turbine could start
rotating until the second cable is connected.
3.
Last, connect the third phase cable.